Weite people fought for 28 days
Helping Guizhou Province's first million-level large-scale hydropower plant
Successful acceptance of the refurbished bridge crane control system
Wujiangdu Power Plant
Wujiangdu Hydropower Station is the first large-scale hydropower station on the mainstream of the Wujiang River. It is a large-scale hydropower station built in a typical karst area in my country. It is also the first one-million-level large-scale hydropower station in Guizhou Province. It is responsible for peak regulation and power transmission in Guizhou power grid. The important task of Guangdong tidal current control main power plant
Wujiangdu Hydropower Station
Wujiangdu Hydropower Station was built by the Eighth Engineering Bureau of the Ministry of Water Resources in April 1970. The entire power station project was completed on December 4, 1982, which lasted 12 and a half years. After 72 hours of trial operation, the power station was officially connected to the grid for power generation on December 4, 1982.
Refurbishment is imminent
The Wujiangdu Hydropower Station is equipped with three high-head large-scale hydroelectric generating units. The stand-alone capacity is 210,000 kilowatts, the total installed capacity is 630,000 kilowatts, and the annual power generation capacity is 3.34 billion kilowatts. Its total installed capacity accounts for about 40% of the total installed capacity of hydro-thermal power in Guizhou Province. The power station was completed and put into production, which increased the power generation capacity of Guizhou Province by about 2/5, and played a key role in the Guizhou power grid.
Project construction seminar
This project is mainly for the refurbishment of the control system of the bridge crane in Wujiangdu No. 2 plant. The bridge crane is the lifting equipment for the expansion plant of Wujiangdu Power Plant in 2002.
Intensive construction on site
The equipment undertook the overhaul of 3 units in the No. 2 plant. At present, overhaul work is imminent, equipment failures frequently occur, and transformation work is urgent.
Efficient refurbishment and smoothly acceptance
After the project won the bid, the hydropower engineer of Weite Technologies Co., Ltd. rushed to Wujiangdu Hydropower Station as soon as possible. After understanding the specific conditions of the entire project, immediately began the refurbishment of the power plant's bridge crane control system.
Weite lifting height limit Switch
After 28 days of intensive construction, it successfully passed the user's three-level acceptance, passed the special inspection and acceptance at one time and obtained the special equipment inspection certificate. The equipment was officially put into operation to ensure the maintenance of the unit in the plant.
Comparison before and after project refurbishment
Project acceptance site
At present, Wujiangdu Power Plant is deeply cooperating with Weite to carry out river basin reconstruction. At the same time, Wujiangdu Power Plant's water inlet door machine control system refurbishment project and bridge crane automatic control scientific research project are under intense construction. In the future, it is expected to realize the automated operation of the entire plant's equipment, providing a strong guarantee for the safety and rapid maintenance of the unit.
Outstanding performance
Relying on excellent construction performance and perfect after-sales service, Weitec Technologies has won numerous fans in the field of crane safety.
In recent years, Weite Technologies Co., Ltd. has become the preferred brand of large and important crane safety monitoring solutions for many domestic and foreign enterprises and construction projects. Weite has won long-term cooperation with hundreds of large domestic enterprise groups with reliable quality and reputation.
Weite has always focused on the research of the safe operation of cranes, providing users with valuable products and services, making the operation of lifting equipment safer and easier to manage.
Add.:No.6 Gangcheng Road,Yichang,Free Trade Zone(Hubei) China 443005
86-15507209968(whatsapp)